== DECEMBER 2009 - COMPLETION STAGES ==

Wednesday, 9th of December, 2009 - Day 89 - Fixing Stage Complete - Completion Stages

We checked the property yesterday, the fencing seems to be taken off now, and they are now working on the floorboards which means its nearly finished. Due to the rain and mud it made it difficult to look through the window. But have caught some pics inside the house.







Friday, 7th of December, 2009 - Day 87 - Fixing Stage Complete - Completion Stages

Haven't updated this for 2 months as all the stuff being done is inside and we cannot get in hence lock up complete, but the summary is that the house interior is almost complete.
Plastering has been done, the electrical's, gas, pipes, ducted cooling and heating is all placed in now.
The house has been painted, the tiling has been done, the facade has been rendered, and our garage has been placed I believe it is about 2 or 3 weeks and the house is done.
The only thing that it needs now is the boundary fencing, and driveway, but that is not important for now.

Here are the photos of the past months of our house in progress.

Front of our house has been rendered and Garage Door Placed


The backyard looking towards the 2nd bathroom

Our backyard, looking towards the kitchen

The front entrance of our house, facade has been rendered.

Our electronic panel garage

House being rendered.

As of October and November, Plastering being done.

The kitchen area of the house pipes sticking out where the bench will be

Kitchen and living area towards the backyard

Laundry area and door to the garage

The front entrance, on the right our masterbedroom

Garage being plastered